Creekside Community 2021 Pavement Rehabilitation

August 14, 2021 / Comments (0)

Civic News Traffic

The City of Ontario has awarded a contract to All American Asphalt of Corona, California to resurface Deer Creek Loop, Day Creek, Elsinore Way, and Haven Avenue.

This work is to begin on Monday, August 23rd, and is anticipated to be completed in November 2021, weather permitting. It will be completed in phases with tentative schedules shown below:

  • ADA Curb Ramp Improvements: August 23rd – September 17th
  • Pavement work: October 5th – November 1st
  • Adjustment of Utilities & Survey Monuments, Striping: November 8th – November 22nd

During this street work, some traffic lanes will be intermittently closed, and traffic will be detoured around the work zone. For your safety, please watch for construction-related signs, including parking restrictions, that will be provided when construction starts. The phasing of this work should be such that access to businesses, schools and residents will be maintained at all times.

As is the case with any construction project of this type, some slight inconvenience may be unavoidable. The City and All American Asphalt will make every effort to minimize your inconvenience during the construction period. Your cooperation with respect to temporary traffic measures and other safety-related signs within the project limits would be greatly appreciated.

Thank you for your patience and understanding during construction of this project.

Should you have any questions regarding the project or special access needs, please feel free to contact Ariana Kern, Assistant Engineer at (909) 395-2401.